| Line | Amount |
|---|---|
| Gross revenue — commercial land resale ($400K/ac × 10 ac; near Holly Springs Business Park — verify with county comps) | $4,000,000 |
| Land acquisition + closing (~2%) | ($2,550,000) |
| Construction — no build; entitlement strategy (residential FAILS at current $265/SF comps at any land cost) | $0 |
| Home On builder margin — N/A | $0 |
| Site development / entitlement costs — survey, planning, legal, rezoning fees, engineering (AT COST) | ($175,000) |
| Contingency (10% of construction, AT COST — typically returned if unused) — N/A | $0 |
| Land loan closing + carry (60% LTV $1.5M loan; 1.5% = $22,500 + 10% APR × 24 months = $300,000) | ($322,500) |
| Selling costs (~7%) — paid at sale closing, not out-of-pocket | ($280,000) |
| NET PROFIT TO INVESTOR | ~$672,500 · 16.8% margin · 43% cash-on-cash (24 months) at $400K/ac — steps to GOOD: achieve $450K/ac commercial → $1,137,500 · 25.3% margin |
Holly Springs new construction sold comps: 749 W Holly Springs Rd $789K/3,008 SF = $262/SF; 743 W Holly Springs Rd $785K/2,944 SF = $267/SF (Triangle MLS late 2025–2026). Residential math: even with zero land cost, construction + site dev + carry on a 30-lot project at $265/SF totals >$17.6M against $22.2M net-of-selling revenue — <20% margin is impossible. Residential = PASS at this price. Commercial comps: FV commercial avg $291K/ac; HS business-park land should command a premium — pull Wake County recorder comps before committing. MAO $2,389,035 at $400K/ac; $2,040,812 MAO at $350K/ac.
The public sewer is the gem — it separates this parcel from every other RR tract in Wake County. But $2.9M cannot be justified on a residential basis at $265/SF comps (math fails regardless of land cost). The commercial entitlement play is MARGINAL at $400K/ac and tips to GOOD at $450K/ac. Negotiate to $2.39M or below before committing. If Holly Springs planning staff support commercial rezoning in this corridor, this becomes a compelling buy; if not, PASS. Recommended action: $2.39M contingent offer, 60-day DD, first 15 days on planning pre-app + county comp pull only.